Dear sandhya,

While doing ck11n for a finished material, only material and material overheads are getting calcualted. The activity type and the production overhead are not getting calculated. Can you please guide me to solve this error?

The error log showing in green colour states that "no structure could be determined for internal activity typexxx"

Diagnosis

The system could not determine a cost component split for the internal activity with activity type XXXX of cost center XXXXX.

Procedure

Check the master data for activity type XXXX of cost center XXXX. It is possible that no activity price calculation has been carried out for the cost center.

I will award full points.